The new WCMA facility is located on the former Williams Inn site near the Williamstown rotary. Two access points have been established to facilitate construction deliveries. The site enabling and pile driving activities are complete, and work on the foundation and stormwater management system is currently in progress. The removal of invasive and unhealthy trees in the reforestation area will continue through June.
Construction Progress Images, May 2025
WCMA Building Drone Flight: June 3, 2025
Monthly Construction Updates
Read our Monthly Construction Update for June 2025.